School Improvement Project
Plans are moving forward with the School Improvement project. Current timelines look like this: (These are subject to change)
Click here to view the construction cam .
* May 2009 construction has begun on the new rooms in the Elementary
* Mid June 2009 Asbestos removal from the older parts of the buildings
* Mid June Outside Site work begins on the parking lots, driveways, football lights and bleachers, softball field relocation, and Elementary playground
* December 2009 Newly constructed Elementary classrooms complete
* January 2010 classroom remodeling begins in older parts of the building
These are just some of the highlights of the building project. All construction is expected to be completed by December of 2010.
|
|
|
|